Road Projects Begin in Milton

Improvements begin all over the city this month.

The city of Milton has a long list of road projects beginning this month, so drivers take note:

Landrum Road Bridge: The replacement of Landrum Road Bridge was scheduled to begin in early July and will take two months.

Ga. 140 (Arnold Mill Road) at New Providence Road: Intersection improvements include redirecting the intersection approach, adding turn lanes and installing a traffic light. The project was scheduled to begin mid-July and is expected to last a year.

Ga. 372 at Providence/New Providence roads: In August, intersection improvements include redirecting the intersection approach and installing a roundabout and will take 18 months.  

Hopewell Road at Francis and Cogburn roads: In August a roundabout will be installed. The project is expected to last a year. Read about tomorrow's Hopewell/Bethany intersection open house here: City Plans to Fix Hopewell Road Intersections.

Deerfield Parkway at Morris Road: In September a traffic signal will be installed. The project will take six months.
For more information, visit miltonintersectionprojects.com, call 678-242-2562 or email orangie.kapijimpanga@cityofmiltonga.us.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here