Milton Starts Road Paving, Reconstruction Projects

The resurfacing program will start first and will be followed by a reconstruction phase.

The city of Milton today will start its fall road paving program, which are slated to continue throughout the first half of September. 

The program is split into two parts--paving and reconstruction, said Public Works Director Carter Lucus.

Weather permitting, roads slated for resurfacing include:

Week 1 (Aug. 19-23)

  • Bray Court
  • Kiltman Court
  • Glendalough Court
  • Buckland Run
  • Providence Lake Drive
  • Lexington Plantation Lane
Week 2 (Aug. 26-30)
  • Wynstead Court
  • Bershire Lane
  • Cannongate Court
  • Petersford Way
  • Croyton Drive
  • Green Road
  • Cogburn Road
Week 3 (Sept. 2-6)
  • Cogburn Road
  • Upland Court
  • Double Creek Lane
  • Mountain Road
Week 4 (Sept. 9-14)
  • Mountain Road
  • Henderson Road
  • Timber Gap Crossing
The next phase of the project will start on Monday Sept. 16, and the city predicts the reconstruction could last around two months. Those roads are: 
  • Hamby Road from Hopewell Road to the Forsyth County line
  • Bethany Road from Providence Road to Alpharetta city limits
  • Dinsmore Road from Freemanville Road to North Valley Road
The city will not completely close roads, but each road will be reduced to one travel lane for motorists. 

For more information, call Public Works Department Citizen Responder Angie Kapijimpanga at (678) 242-2562 or angie.kapijimpanga@cityofmiltonga.us.

Don’t miss any Alpharetta-Milton news. Subscribe to Alpharetta-Milton Patch’s  free newsletter, like us on  Facebook and follow us on Twitter.

Find out what's happening in Alpharetta-Miltonwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here